Management of Change (MOC): Safely Navigating Workplace Transitions
MOC for your process safety management

Change is inevitable; loss of control isn’t. MOC is how you keep safety steady while everything else shifts.

When equipment, materials, software, or procedures change, risk changes with them. Management of Change (MOC) is the structured process that evaluates, approves, and verifies changes before they impact people, plant, or product. It’s a core expectation in global standards (e.g., OSHA PSM, ISO 45001) and a proven guardrail against incidents and unplanned downtime. Done well, MOC turns “we didn’t see that coming” into “we anticipated it and built protections in.”

This how-to guide lays out when to trigger MOC, a practical end-to-end workflow, common pitfalls, and the governance elements that keep your program effective. It also shows exactly how OQSHA supports each step so teams can manage change with clarity and confidence.

What counts as a “change”?

Introduction to MOC

Not every replacement needs MOC. Replacement-in-kind (RIK)—swapping like-for-like components with no new hazards—typically does not require full MOC. Everything else is a candidate.

Trigger MOC for:

  • Process/equipment changes: setpoints, software/logic (PLC/DCS), interlocks, control narratives, capacity, materials of construction, utilities, layouts.
  • Materials changes: new raw materials or suppliers, concentration/purity changes, new chemicals or intermediates.
  • Procedure changes: start-up/shutdown steps, permit requirements, maintenance methods, emergency response plans.
  • People/organization changes: staffing levels, role definitions, new contractors or outsourcing critical tasks.
  • Safeguards changes: alarms, trips, relief systems, ventilation, PPE requirements.
  • Facility changes: rerouting lines, adding tie-ins, confined space reclassification.

When in doubt, initiate a screening MOC—it’s better to de-scope a change than to miss a critical review.

The MOC workflow (10 steps that work)

  1. Initiate & classify the change
    Capture the who/what/where/why and proposed go-live date. Classify the change (process, equipment, procedural, organizational) and assign a preliminary risk category to set the review depth.
  2. Define scope & boundaries
    Document the full envelope: affected equipment, documents, procedures, roles, and upstream/downstream impacts. Scope creep is a classic MOC failure—lock it down early.
  3. Impact analysis (multidisciplinary)
    Convene operations, engineering, maintenance, EHS, quality, and (if relevant) contractors. Assess impacts on safety, operability, reliability, product quality, environmental compliance, and ergonomics.
  4. HIRA / risk assessment
    Use an appropriate method (risk matrix, JSA, What-If/HAZID, or HAZOP for higher-hazard processes) to identify new/changed hazards and define additional safeguards. Record pre- and post-mitigation risk to show the delta.
  5. Regulatory & standards check
    Verify implications for permits, statutory inspections, codes/standards, and required notifications. Update SDSs/labels where materials change.
  6. Define safeguards & actions (CAPA)
    Translate risks into specific actions: engineering controls, interlocks, alarm limits, procedures, training, spares, signage, PPE, inspection intervals. Assign owners and due dates with clear acceptance criteria.
  7. Documentation updates
    Redline and then issue controlled versions of all impacted documents: P&IDs, cause-and-effect charts, SOPs, LOTO, emergency plans, training materials, permits, and checklists.
  8. Approvals & go/no-go gate
    Obtain approvals from process owner, EHS, engineering, and site leadership—only after all pre-start actions are complete or explicitly deferred with risk justification and compensating controls.
  9. Communication, training & readiness
    Brief affected teams and contractors. Conduct targeted training and competency checks (e.g., simulations for start-up/shutdown changes). Confirm spares/tools are on hand.
  10. PSSR & post-implementation review
    Perform a Pre-Startup Safety Review (PSSR) to verify the plant matches the paperwork. After start-up, monitor KPIs and near misses, capture lessons learned, and formally close the MOC when acceptance criteria are met.

Roles & responsibilities (RACI-lite)

  • Initiator: Raises the change, drafts initial scope.
  • Process Owner: Accountable for outcomes; ensures resources and compliance.
  • EHS/Safety: Facilitates HIRA, validates safeguards, coordinates PSSR.
  • Engineering/Maintenance: Designs changes, updates drawings, ensures reliability.
  • Operations: Validates practicality, informs procedures and training.
  • Quality/Regulatory: Confirms standards and documentation requirements.
  • Contractors/Vendors: Provide technical data, comply with site MOC rules.
  • Approvers (site leadership): Authorize risk acceptance and go-live.

Common pitfalls—and how to avoid them

Common pitfalls we observe for MOC
  • “Hidden” changes: Minor tweaks to control logic, alarm setpoints, or SOPs slip through.
    Fix: Mandatory MOC screening for all logic/procedure edits and a monthly audit of change logs.
  • Scope creep: Field realities expand work beyond the reviewed envelope.
    Fix: Freeze scope, require a linked MOC for any additions.
  • Paper vs. plant mismatch: Documentation updated, but hardware or training lags.
    Fix: PSSR with walkdowns, tag-to-drawing verification, and sign-off by ops/EHS.
  • Incomplete training: Shift coverage and contractors miss the update.
    Fix: Competency tracking with 100% sign-off before start; include night/weekend crews.
  • Weak close-out: Actions drift; lessons aren’t captured.
    Fix: Close-out review with KPIs (see below) and a required “lessons learned” note.

History is blunt: major incidents—from Flixborough (1974) to Texas City (2005)—trace back to uncontrolled changes and missing safeguards. A disciplined MOC breaks that chain.

Governance & metrics that matter

Track a handful of leading/lagging indicators to keep your MOC program healthy:

  • Time-to-approve changes (by risk class).
  • % MOC actions closed on time; number of overdue high-risk actions.
  • Training/competency completion for affected roles (100% before start).
  • PSSR findings per change and rework required.
  • Residual risk delta (pre- vs. post-mitigation).
  • Incidents/near misses post-change within 30/90 days.
  • Audit conformance: sample MOCs fully traceable (initiation → PSSR → close-out).

Embed monthly reviews in your safety committee and quarterly leadership dashboards.

What to capture on your MOC form (field checklist)

  • Change title, description, initiator, location/equipment ID
  • Reason/business driver, proposed date, change class (process/equipment/procedure/org)
  • Impacted documents (P&IDs, SOPs, permits, training, drawings)
  • HIRA reference and summary of risks/safeguards
  • Regulatory/permit impacts; relief/venting implications if applicable
  • Action register (owner, due date, acceptance criteria)
  • Training/communication plan and completion evidence
  • Approvals (names, dates)
  • PSSR checklist and sign-off
  • Post-implementation review notes; lessons learned
  • Final close-out date and document version links

How OQSHA supports effective MOC

Plan & evaluate

  • MOC workflow with configurable risk classes, reviewers, and multi-level approvals.
  • Linked HIRA: run risk assessments within the MOC, record pre/post risk, attach evidence.
  • Standards/permit fields to record regulatory checks and notifications.

Execute & verify

  • Action tracker (CAPA) with owners, SLAs, escalations (email/WhatsApp/in-app), and audit trail.
  • Document hub for controlled SOPs, P&IDs, and redlines; version history stays immutable.
  • Training & competency module to assign courses, track completion, and block start-up until 100% trained.
  • PSSR checklists tied to the MOC; go-live gated on PSSR sign-off.

Monitor & improve

  • Dashboards & KPIs: time-to-approve, overdue actions, residual risk deltas, PSSR findings, post-change near misses.
  • Multi-site roll-ups to compare change performance across plants, lines, or contractors.
  • Evidence vault with geo-tagged photos/videos and e-signatures for audit readiness.

Result: one connected trail from idea → risk review → approvals → training → PSSR → closure.

Quick MOC readiness checklist

  • MOC triggers defined and communicated (incl. software/logic and procedural edits).
  • Screening step in place; every change gets captured or documented as RIK.
  • Multidisciplinary impact analysis and HIRA performed for non-RIK changes.
  • Regulatory/permit review completed and documented.
  • Actions (engineering/procedural/training) assigned with clear owners and due dates.
  • Controlled documents updated; redlines closed.
  • Training completed (including contractors and all shifts).
  • PSSR performed with physical verification and sign-offs.
  • Post-start monitoring plan set; lessons learned captured.
  • KPIs reviewed monthly; audits confirm traceability.

Control the change, protect the operation

OQSHA for your MOC processes

Unmanaged change is one of the fastest ways for risk to sneak into otherwise well-run operations. A disciplined MOC—anchored in clear triggers, rigorous risk review, real-world training, PSSR verification, and KPI-driven governance—keeps your people safe and your processes dependable. With OQSHA’s end-to-end MOC, HIRA, training, CAPA, and PSSR capabilities on web and mobile, you gain the visibility and accountability to move fast and stay safe—every change, every time.